Independent investigators released their final report Jan. 5 on the flood at a northern California dam in February 2017. "In a 584-page dissection of the disaster at America's tallest dam, the investigative team said Oroville Dam was designed and built with flaws from the beginning, which were exacerbated by inadequate repairs in the years that followed," Dale Kasler reports for the Sacramento Bee. The investigation team was made up of six independent engineering consultants from around the country.

Nearly 200,000 people were evacuated from the area downstream of the dam in early February 2017 when engineers discovered damage to the spillways after heavy rains. Repair of the dam is estimated to cost $500 million. The dam was inspected regularly before the disaster, but in the interim report released Sept. 5, investigators said the inspectors relied too heavily on visual inspections to catch the problem.


"Due to the unrecognized inherent vulnerability of the design and as-constructed conditions and the chute slab deterioration, the spillway chute slab failure, although inevitable, was unexpected," the panel report said.

The investigators also warned the entire dam industry to pay attention, since about 14,000 of the more than 87,000 dams in the U.S. are classified as "high hazard potential".

Dams at risk of failure (FEMA map; click the image to enlarge it)



from The Rural Blog http://ift.tt/2FeO1IQ Investigators say Oroville dam disaster the result of 'long-term systemic failure' - Entrepreneur Generations